18 flats and family houses for a registered provider in Wiltshire: 4 one bed flats, 4 two bed houses and 10 three bed houses, made from 32 modules. All 18 homes are made in one production run and shipped together. We post each milestone here. Completion is due in May 2027.
Final factory works
The modules for all 18 homes are at the TLC Modular factory in Vietnam for their final works: second fix services, underfloor heating, decoration, cladding and windows. Every module gets its own inspection record, signed off before it is closed up.
Full Plans Approval
Building Control issued Full Plans Approval for the scheme's modular design. All 22 plan check items on the revised design were closed before approval.
Foundations approved on all 18 plots
Building Control inspected and approved the insulated raft foundations on every plot. Rafts, drainage and utility connections are in place, ready for the modules to be craned on.
Levelling the bed for a raft.Insulated raft formwork before the pour.
Back on site
Groundworks restarted on site, with the rafts, drainage and service connections for all 18 plots.
Visualisation of the finished scheme.
What happens next
Pre-shipment inspection of every module at the factory.
One shipment to a UK port, about 5 weeks at sea.
Modules craned onto the rafts, then joints, services, connections and testing.